Code No: NR 220401
Supplementary Examinations November-2003
Set No. 3
MANAGEMENT SCIENCE
(Common to Electronics & Communication Engineering, Electronics & Telematics)
[Time:3 hours]
Max. Marks:80
Answer any FIVE questions
All questions carry equal marks
1. What are the essential characteristics of management? Is Management Science an exact one as in the case of Physics, Chemistry etc? Explain.
2. What is mission? What are the determinants of mission?
3. Discuss the main techniques of statistical quality control.
4. What is job evaluation? What are its advantages?
5. a) Discuss the procedure usually adopted for the receipt and issue of items in a stores.
b) Discuss the various types of records and registers to be maintained in stores.
6. What is 'Consumer orientation'? Explain the important stages of developing suitable marketing process for:
i) manufactured products and ii) services.
7. A project consisting of 12 distinct activities is to be analysed by using PERT. Draw the PERT network. Indicate the expected total slack for each activity and hence indicate the average critical path. With in how many days would you expect the project to be completed with 99% chances?
| ACTIVITY | PREDECESSOR ACTIVITY | OPTIMISTIC TIME (Days) | NORMAL TIME (Days) | PESSIMISTIC TIME (Days) |
| A | - | 2 | 2 | 2 |
| B | - | |||
| 1 | 3 | 7 | ||
| C | A | 4 | 7 | 8 |
| D | A | 3 | 5 | 7 |
| E | B | 2 | 6 | 9 |
| F | B | 5 | 9 | 11 |
| G | C,D | 3 | 6 | 8 |
| H | E | 2 | 6 | 9 |
| I | C,D | 3 | 5 | 8 |
| J | G,H | 1 | 3 | 4 |
| K | F | 4 | 8 | 11 |
8. The following table gives the information about various activities of a project network.
| Activity | Normal duration (Days) | Normal Cost (Rs.) | Crash duration (Days) | Crash Cost (Rs.) |
| 1-2 | 9 | 8000 | 7 | 10,000 |
| 1-3 | 5 | 5000 | 3 | 8,000 |
| 2-3 | 7 | 7000 | 5 | 8,600 |
| 2-3 | 8 | 6000 | 6 | 7,000 |
| 3-4 | 6 | 9000 | 4 | 11,400 |
The overhead costs are Rs 1300 per day. Determinant the optimum cost and duration of the project.
Business Schools - Engineering Colleges - Medical & Nursing Admissions - BEd in Distance mode - Journalism & Media Studies - IGNOU
B School Admissions
Do check out Admissions for Business, Management & Commerce courses
Business Schools Directory
Browse through the complete List of Top Business Schools in India
Quiz Time!!
Did you try our latest Business Quiz - Finance
Test your knowledge on Business & Finance terminology..
Enter a detailed keyword. Ex: Question Papers of Jawaharlal Nehru Technological University MCA Ist Semester