MANAGEMENT PROGRAMME
Term-End Examination
June, 2005
MS-53 : PRODUCTION/OPERATIONS MANAGEMENT
Time: 3 hours
Maximum Marks: 100
SECTION A
1. (a) Explain what you understand by the term "Total Quality Management", paying particular attention to
the following terms :
quality, supplier-customer interfaces, and process.
(b) Define Productivity. List some factors that can affect productivity and some ways in which productivity can be improved.
2. (a) Give two examples (with supporting details) of the impact of technology in product and service design, in the context of service and manufacturing firms.
(b) A firm uses simple exponential smoothing with α = 0.1 to forecast demand. The forecast for the first week of February was 500 units, whereas actual demand turned out to be 450 units.
(i) Forecast the demand for the second week of February.
(ii) Assume that the actual demand during the second week of February turned out to be 505 units. Forecast the demand for the third week of February.
3. (a) Bloomsday Outfitters produces T-shirts for road races. They need to acquire some new stamping machines to produce 30,000 good T-shirts per month. Their plant operates 200 hours per month, but the new machines will be used for T-shirts only 60 percent of the time and the output usually includes 5 percent that are "seconds" and unusable. The stamping operation takes 1 minute per T-shirt, and the stamping machines are expected to have 90 percent efficiency considering adjustments, changeover of patterns, and unavoidable downtime. How many stamping machines are required ?
(b) Give an example of a business that would use a push and one that would use a pull operations control system. Explain your choice and briefly describe how the system works.
4. (a) What factors should be taken into account when taking make-or-buy decisions ? Illustrate your answer with examples from both a manufacturing and service organisation.
(b) What are the two major uncertainties encountered in managing inventories and what is usually done to compensate for those uncertainties?
5. (a) What are the various methods of judgemental forecasting ? Comment on possible errors that are associated with judgemental forecasting.
(b) A time study of a restaurant activity yielded a cycle time of 2.00 minutes, and the waitress was rated at PR = 96 percent. The restaurant chain has a 20 percent allowance factor, Find the standard time.
SECTION B
6. (a) What are the advantages of having a company-wide data-bank ? Show how different functions e.g. cost accounting, sales, inventory, manufacturing can be integrated with a data-bank.
(b) A contractor has to supply 10,000 bearings per day to an automobile manufacturer. He finds that, when he starts a production run, he can produce 25,000 bearings per day. The cost of holding a bearing in stock for one year is Rs. 2 and the set-up cost of a production run is Rs. 1,800. How frequently should production runs be made ? (Assume 300 working days in a gear)
7. Write short notes on any five of the following :
(a) Cellular manufacturing
(b) ISO 9000
(c) Fish-bone Diagram
(d) AGVS
(e) Cross Impact Matrix
(f) Benchmarking
(g) CIM
(h) Job Enlargement
The following is a partial list of Testpapers of similar / related courses to Production / Operations Management offered by IGNOU
Business Schools - Engineering Colleges - Medical & Nursing Admissions - BEd in Distance mode - Journalism & Media Studies - IGNOU
B School Admissions
Do check out Admissions for Business, Management & Commerce courses
Business Schools Directory
Browse through the complete List of Top Business Schools in India
Quiz Time!!
Did you try our latest Business Quiz - Finance
Test your knowledge on Business & Finance terminology..
Enter a detailed keyword. Ex: Question Papers of IGNOU MCA Ist Semester